Update as of Aug. 1, 2024
The Hot tub replacement project was tendered May 31, 2024 with a closing date of June 27th, 2024. The approved 2024 capital budget included $750,000 for the construction project which included the full reconstruction of the hot tub. Upon the closing date one submission was received.
The proposal received included a price of $1.3 million, which is $550,000 over the approved budget.
The tender has been cancelled due to the significant difference in the submission and the approved budget. The project will be reevaluated in collaboration with the 2025 capital budget process.
RFQ: Peace Regional Pool Hot Tub Replacement Project
UPDATED: June 15, 2024
ATTN: Tanya Bell
Town of Peace River Town Office
9911-100 St. PO Box 6600
Peace River, AB, T8S1S4
PLEASE NOTE:It is proponents’ responsibility to ensure they are aware of all tender addendums created for this project, which are included below and on the Alberta Purchasing Connection portal.